10/02/2026
Work on the new high school building is progressing well, with strong momentum on foundational structures. Below is a summary of recent accomplishments and upcoming milestones.
Recent Progress (Week of October 2)
-
Foundations & Structure:
-
Completed perimeter footings for Area A and Area B.
-
Completed concrete foundation walls for Area A and Area B.
-
Began foundational work for Area E (Gym).
-
-
Site Preparation & Utilities:
-
Completed stone placement and fine grading for the bus lot.
-
Continued progress on stormwater utilities and temporary construction access roads.
-
Upcoming Schedule
Week of October 5
-
Masonry & Foundations:
-
Construct masonry foundation walls for Area E, Area A, and Area B.
-
Pour Area E (PR-02) footings and progress on interior foundations for Area A and Area B.
-
-
Site Utilities & Infrastructure:
-
Continue work on stormwater utilities and temporary construction access roads.
-
Install underground plumbing for Area A.
-
Begin underground electrical installation for site lighting.
-
Week of October 12
-
Continue ongoing installation of stormwater and sanitary utilities.