Work on the new high school building is progressing well, with strong momentum on foundational structures. Below is a summary of recent accomplishments and upcoming milestones.

Recent Progress (Week of October 2)

  • Foundations & Structure:

    • Completed perimeter footings for Area A and Area B.

    • Completed concrete foundation walls for Area A and Area B.

    • Began foundational work for Area E (Gym).

  • Site Preparation & Utilities:

    • Completed stone placement and fine grading for the bus lot.

    • Continued progress on stormwater utilities and temporary construction access roads.

Upcoming Schedule

Week of October 5

  • Masonry & Foundations:

    • Construct masonry foundation walls for Area E, Area A, and Area B.

    • Pour Area E (PR-02) footings and progress on interior foundations for Area A and Area B.

  • Site Utilities & Infrastructure:

    • Continue work on stormwater utilities and temporary construction access roads.

    • Install underground plumbing for Area A.

    • Begin underground electrical installation for site lighting.

Week of October 12

  • Continue ongoing installation of stormwater and sanitary utilities.