10/16/2026 Construction Update

 Back To District News

10/16/2026 Construction Update

Oct 20, 2026
foundations
New High School

Work continues to progress smoothly across the new Monroe High School site and construction crews are taking advantage of the nice weather! Here is a look at what our construction team accomplished this past week and what is on the schedule for the coming weeks: click here for weekly photos

Work Completed This Week

  • Site & Utilities: Completed underground sanitary utility work and installed underground electrical infrastructure for site lighting.

  • Foundations & Structure: Poured footings in Areas C and F. Masonry foundation walls were constructed across Areas A, B, E, and F.

  • Plumbing: Completed underground plumbing installations across Areas A, B, and E.

Looking Ahead: Week of October 19

  • Utilities & Infrastructure: Crews will focus heavily on site utilities, including primary electrical service, site lighting, and utility connections for sanitary, stormwater, water, and the new drive.

  • Foundations & Masonry: Footing pours will continue in Areas C and D, alongside ongoing masonry foundation wall construction in Areas A and B.

  • Underground Services: Underground plumbing and electrical work will expand across Areas A, B, E, and F.

Looking Ahead: Week of October 26

  • Site & Earthwork: Utility installations for water, gas, and stormwater will continue, alongside grading work for the new drive.

  • Structural Milestones: Crews will pour footings in Area D, prep and pour the slab-on-grade for Area A, and begin erecting bearing walls for the Area E Gymnasium.

  • Underground Services: Underground plumbing and electrical work will transition into Area C.

We will continue to share weekly updates as our new high school takes shape. Thank you for your continued support of Monroe Local Schools!