10/30/2026 Construction Update

NOV 2, 2026

Here is the weekly construction update on the progress of our new Monroe High School, based on the latest report from Robertson Construction. photos

  • Masonry & Structure: Construction of masonry bea...
HS Construction

10/23/2026 Construction Update

OCT 23, 2026

We have walls!!

Below is the weekly progress report from Robertson.

Work continues to advance on the new Monroe High School project under the direction of Robertson Construction Services and Fanning...

foundations

10/16/2026 Construction Update

OCT 20, 2026

Work continues to progress smoothly across the new Monroe High School site and construction crews are taking advantage of the nice weather! Here is a look at what our construction team accomplished th...

10/09/2026 Construction Update

OCT 9, 2026

Thanks to favorable weather conditions, our construction team continues to make significant strides across the building foundation areas and overall site infrastructure.

 

Recent Progress (Week of O...

Map

10/02/2026 Construction Update

OCT 2, 2026

Work on the new high school building is progressing well, with strong momentum on foundational structures. Below is a summary of recent accomplishments and upcoming milestones.

 

Recent Progress (We...