11/13/2026 Construction Update
Here is the weekly construction progress update for Monroe High School based on the latest report from Robertson Construction: Weekly Photos
- Over the past week, work crews have made steady progress across the site. Exterior site lighting installation has been ongoing, while interior and underground utility work advanced significantly. Crews successfully poured the slab on grade in Area B and continued constructing the masonry bearing walls in Area E. Additionally, underground plumbing and electrical rough-ins are well underway in Areas C, D, and F.
- Looking ahead to the week of November 16, outdoor and site work will continue with ongoing site lighting installation, electrical primary ductbank work, the start of gas houseline installations, and continued water main work (pending final permits). Crews will also place fine grade stone and the base course asphalt on the parking lots and new drive. Inside the building, masonry bearing walls will rise further in Area E, prep work for the slab on grade will take place in Area C, and underground plumbing will continue in Area F.
- During the week of November 23, construction will progress with the completion of the new drive's asphalt finish, continued gas houseline and site lighting installations, and ongoing water main work. Masonry bearing walls in Area E and underground plumbing in Area F will also proceed, alongside the planned slab on grade pour in Area C.