10/30/2026 Construction Update

Nov 2, 2026
construction
Gymnasium wall

Here is the weekly construction update on the progress of our new Monroe High School, based on the latest report from Robertson Construction. photos

  • Masonry & Structure: Construction of masonry bearing walls progressed in Area E.
     
  • Slab Preparation: Area A slab-on-grade prep work was completed.
     
  • Site Lighting: Installation began for high school site light pole bases.
     
  • Utilities & Rough-Ins: Electrical and plumbing in-wall rough-ins continued in Area E, with underground plumbing and electric installation underway in Area D and Area F.
     

Current Focus (Week of November 2)

  • Concrete Pours: Concrete pour scheduled for Area A slab on grade, along with slab-on-grade prep starting for Area B.
  • Masonry & Rough-Ins: Continued work on Area E masonry bearing walls and in-wall electrical and plumbing rough-ins.
  • Underground Utilities: Underground plumbing and electrical work continuing in Area F and beginning in Area C.
     
  • Site Infrastructure: Light pole base installation extending to both the high school site and the new drive.
     

Looking Ahead (Week of November 9)

  • Drive & Site Prep: Fine-grade stone work on the new drive and ongoing installation of site light pole bases.
     
  • Main Utilities: Installation of the gas houseline, fire water mains, and domestic water mains.
     
  • Slab Construction: Area B slab-on-grade pour and Area C slab-on-grade prep.
     
  • Ongoing Building Work: Continued masonry bearing walls and rough-ins in Area E, alongside underground utility work in Area C and Area F.
     

Roadway & Access Updates

  • Yankee Road: Road improvements are well ahead of schedule, with reopening targeted for Wednesday, November 4.
  • New Drive: Construction remains on track to open the second drive later this school year.