10/30/2026 Construction Update
Here is the weekly construction update on the progress of our new Monroe High School, based on the latest report from Robertson Construction. photos
- Masonry & Structure: Construction of masonry bearing walls progressed in Area E.
- Slab Preparation: Area A slab-on-grade prep work was completed.
- Site Lighting: Installation began for high school site light pole bases.
- Utilities & Rough-Ins: Electrical and plumbing in-wall rough-ins continued in Area E, with underground plumbing and electric installation underway in Area D and Area F.
Current Focus (Week of November 2)
- Concrete Pours: Concrete pour scheduled for Area A slab on grade, along with slab-on-grade prep starting for Area B.
- Masonry & Rough-Ins: Continued work on Area E masonry bearing walls and in-wall electrical and plumbing rough-ins.
- Underground Utilities: Underground plumbing and electrical work continuing in Area F and beginning in Area C.
- Site Infrastructure: Light pole base installation extending to both the high school site and the new drive.
Looking Ahead (Week of November 9)
- Drive & Site Prep: Fine-grade stone work on the new drive and ongoing installation of site light pole bases.
- Main Utilities: Installation of the gas houseline, fire water mains, and domestic water mains.
- Slab Construction: Area B slab-on-grade pour and Area C slab-on-grade prep.
- Ongoing Building Work: Continued masonry bearing walls and rough-ins in Area E, alongside underground utility work in Area C and Area F.
Roadway & Access Updates
- Yankee Road: Road improvements are well ahead of schedule, with reopening targeted for Wednesday, November 4.
- New Drive: Construction remains on track to open the second drive later this school year.