construction

10/30/2026 Construction Update

NOV 2, 2026

Here is the weekly construction update on the progress of our new Monroe High School, based on the latest report from Robertson Construction. photos

  • Masonry & Structure: Construction of masonry bea...
Drone image of Monroe's current 2-12 main campus and athletic facility, with the foundation of the new high school beginning to take shape in the foreground.

New $62M high school, Yankee Road connector transforming Monroe Schools' main campus

OCT 23, 2026

Michael D. Clark | Journal-News

 

Progress continues on two of the most impactful projects in the history of Monroe Schools’ main campus transforming the school grounds with a new high school and a ...

HS Construction

10/23/2026 Construction Update

OCT 23, 2026

We have walls!!

Below is the weekly progress report from Robertson.

Work continues to advance on the new Monroe High School project under the direction of Robertson Construction Services and Fanning...

foundations

10/16/2026 Construction Update

OCT 20, 2026

Work continues to progress smoothly across the new Monroe High School site and construction crews are taking advantage of the nice weather! Here is a look at what our construction team accomplished th...

Yankee Road detour map

Yankee Road Closure: Oct. 19 - Nov. 20, 2026

OCT 19, 2026
Please be aware that beginning Monday, Oct. 19, Yankee Road will be closed to all through traffic north of Hornet Drive for 33 days. The road is currently expected to reopen on Nov. 20, 2026, weathe...

10/09/2026 Construction Update

OCT 9, 2026

Thanks to favorable weather conditions, our construction team continues to make significant strides across the building foundation areas and overall site infrastructure.

 

Recent Progress (Week of O...

Map

10/02/2026 Construction Update

OCT 2, 2026

Work on the new high school building is progressing well, with strong momentum on foundational structures. Below is a summary of recent accomplishments and upcoming milestones.

 

Recent Progress (We...

An aerial drone photo of the cleared high school construction site looking north, with the the athletic complex in the background

Work starting on new $62M Monroe HS is 'massive milestone' for district, superintendent says

AUG 18, 2026

Michael D. Clark | Journal-News

 

Construction noise mixed with the sounds of back-to-school excitement this week at Monroe Local School District’s main campus as earth-moving crews prepared the gro...

"Important Information" news graphic

2026-27 Back-to-School Hub

JUL 12, 2026

Important news and updates to help you prepare for the 2026-27 school year.

Copied!
^TOP
close
ModalContent
loading gif